Update No.15 14th July 2016
Progress. A busy couple of week. Distillery conversion has been progressing fantastically well and we have started receiving plant equipment….. THE POT STILLS ARRIVE NEXT WEEK!!! This week the builders have laid external concrete pathways, replaced cast iron gutters and finalised the electrical plans. We have also received friends from NYC and Japan who are…
-
Update No.14 1st July 2016
Up’s and Downs…. This week has been particularly testing. We were massively let down by a bottle manufacturer, however we can overcome almost anything. These moments were meant to test us and we have (almost) found a good solution! On a more positive note we have overcome various issues and the builders and joiner have…
-
Update No.13 23rd June 2015
Joining the dots…… Another wonderfully productive week has passed. Our joiner has been working incredibly hard creating doorways, floors and hanging the doors! We have started receiving delivery dates for a lot of the larger pieces of equipment… It is all becoming very real! There was a visit from one of our cask suppliers. They…
-
Update No.11 3rd June 2016
We are coming to the close of a fantastically productive week here in Dornoch! The builders have put in a power of work ensuring the water and three-phase electricity have been correctly connected! They have also almost finished the internal pointing, which looks awesome! Yesterday we received all out ATEX LED strip lights. A lot…
-
Update No.10 26th May 2016
Hello everyone! We have been incredibly busy here over the pas couple of weeks. The builders have been making great progress. We have been working on bottle designs and sourcing various Organic botanicals for our #milltostill Gin. Tomorrow SSE are coming to hook up our three-phase electricity. Next week we should have the water plumbed into…